Difference between revisions of "Economics (Sustainability Assessment)"
Line 42: | Line 42: | ||
For consistency, the IRR needs to be calculated using a similar modelling process as chosen for calculating LUEC. So, if inflation is not included in calculating LUEC, it would not be included in calculating IRR. In this case, the IRR would be less than what would arise from a model that included inflation.<br> | For consistency, the IRR needs to be calculated using a similar modelling process as chosen for calculating LUEC. So, if inflation is not included in calculating LUEC, it would not be included in calculating IRR. In this case, the IRR would be less than what would arise from a model that included inflation.<br> | ||
The IRR would normally be calculated for the total cash flow of a single NPP. As for LUEC, the economics of fuel cycle facilities is covered within the fuel costs of the NPP. So, if it is foreseen that the price of uranium is expected to increase over the life of the NPP, such a price increase should be reflected in the fuel cost used in the analysis. Only costs and credits that are defined in the price setting mechanism should be considered. Externalities should be excluded if they are not supported by an acknowledged price calculation process. <br> | The IRR would normally be calculated for the total cash flow of a single NPP. As for LUEC, the economics of fuel cycle facilities is covered within the fuel costs of the NPP. So, if it is foreseen that the price of uranium is expected to increase over the life of the NPP, such a price increase should be reflected in the fuel cost used in the analysis. Only costs and credits that are defined in the price setting mechanism should be considered. Externalities should be excluded if they are not supported by an acknowledged price calculation process. <br> | ||
− | The acceptance limit '''AL2.1.1''' for evaluation parameter '''EP2.1.1''' reads as follows | + | The acceptance limit '''AL2.1.1''' for evaluation parameter '''EP2.1.1''' reads as follows: <br> |
Acceptance limit '''AL2.1.1''': <math>IRR_N > IRR_A</math><br> | Acceptance limit '''AL2.1.1''': <math>IRR_N > IRR_A</math><br> | ||
The internal rate of return IRRN of an investment into a NES should be comparable, i.e. higher or at least equal than IRRA an investment in competing (alternative) energy technologies. | The internal rate of return IRRN of an investment into a NES should be comparable, i.e. higher or at least equal than IRRA an investment in competing (alternative) energy technologies. |
Revision as of 07:03, 16 July 2020
INPRO Economic Basic Principle (BP) - Energy and related products and services from nuclear energy systems shall be affordable and available.
Contents
UR1 (Cost of energy)
The definition of UR1 is: The cost of energy supplied by nuclear energy systems, taking all relevant costs and credits into account, CN, must be competitive with that of alternative energy sources, CA, that are available for a given application in the same time frame and geographic region/jurisdiction.
This UR relates to the cost competitiveness of different energy sources available in a country, region, or globally. In comparing the costs of electricity (or other energy products) from a NES, CN, and competing alternatives, CA, discounted costs (LUEC) are used. In this comparison all relevant costs are to be included.
Depending on the jurisdiction in a country, one energy source may be burdened with costs, e.g. for waste management, while another may not. In a number of Member States, the external costs of nuclear power that are not accounted for are small, since producers are required by law to make provisions for the costs of waste management, including disposal, and decommissioning, whereas the external costs of competing (non-nuclear) energy sources that are not accounted for may be significant, e.g. CO2 emission from fossil power plants. Ideally, all external costs should be considered and, where possible, internalized, when comparing a NES with competing energy systems, but only costs that are internalized (in the price to the consumer) should be taken into account, and other external costs should be ignored.
CR1.1: Cost competitiveness
ᅠ Indicator IN1.1: Cost of energyᅠ
|
---|
The value of indicator IN1.1, i.e. costs of energy (CN and CA) of competing energy supply options to be deployed, is determined using a discounted cost (LUEC) model[8], taking into account all relevant cost determinants for both the NES and the competing energy technology. |
ᅠ Acceptance limit AL1.1ᅠ
|
---|
AL1.1 is defined as: |
UR2 (Ability to Finance)
The definition of UR2 is: The total investment required to design, construct and commission nuclear energy systems, including interest during construction, should be such that the necessary investment funds can be raised.
There are two aspects to investment, somewhat related to each another, namely, the attractiveness of the investment in terms of the financial return to be expected and the size of the investment that is required. Even if the financial indicators used to analyse return are attractive, a given utility may not have the wherewithal to raise the funds needed — neither from its own resources nor from other investors.
The total investment required to deploy a given NES, or component thereof, comprises the costs to adapt a given design to a given site, and then to construct and commission the plant, including the interest during construction. The latter depends on construction time and the time to commission. A universally applicable criterion for what constitutes an acceptable ‘size’ of investment cannot be defined a priori since this will vary with time and region and will depend on many factors, such as alternatives available, etc. But a judgment must be made that the funds required to implement a project can be raised within a given expected investment climate. Factors influencing this ability may include the overall state of the economy of a given region/country, the size of the investment relative to a utility’s annual cash flow (and hence the size of the unit relative to the size of the grid), and the size of the investment compared with that needed for alternative sources of supply.
The attractiveness of an investment may be expected to have some influence on the acceptability of the size of the investment but in the INPRO methodology the two are treated as independent. Since, however, there is some influence of attractiveness on acceptability of size, we treat attractiveness first.
The attractiveness of an investment is usually quantified by determining economic parameters called financial figures of merit. Examples of such figures are IRR, the ROI, NPV of cash flows, and payback period. IRR and NPV are more or less two sides of the same coin, as are ROI and payback time.
CR2.1: Attractiveness of investment
ᅠ Indicator IN2.1: Financial figures of merit ᅠ
|
||||||
---|---|---|---|---|---|---|
Acceptance limit AL2.1: Figures of merit for investing in a NES are comparable with or better than those for competing energy technologies.
Investors can look at a variety of financial indicators when evaluating investments. The financial indicators used in a given region will reflect the investment climate and requirements of a given country or region, including the source(s) of investment funds. In some countries or regions implementation of a NES will require private sector investment, e.g. in deregulated electricity markets, while in other countries or regions installment of a NES may require government investment or guarantees, e.g. in countries embarking on a nuclear power programme.
For final assessment of acceptance limit AL2.1: |
CR2.2: Affordability of investment
Indicator IN2.2 is defined as: The highest single plant total investment up to commissioning the reactor within a complete NES.
Acceptance limit AL2.2: The total investment required should be compatible with the ability to raise capital in a given market climate.
ᅠ Indicator IN2.2: Total investment ᅠ
|
---|
The total investment consists of the overnight capital, the interest during construction (the size of which depends on construction and commissioning times), contingency allowances, owners cost and (if not considered in the O&M cost) the capital needed for (foreseen) back fitting and decommissioning. It can be calculated using the NEST tool.
In effect, the acceptance limit for deployment of the first few NPPs in a country is that the total investment required should be compatible with the ability to raise the necessary capital in the country at the time of committing to construction of the NPP. And for the deployment of additional units of the same basic type of NPP, the acceptance limit is that the total investment required is compatible with the ability to raise the necessary capital in the country at the time of committing to construction of the additional units, taking into account actual performance and costs for nuclear power in the country. |
[ + ] Assessment Methodology | |||||
---|---|---|---|---|---|
|